Elevator fire safety planning for a building in Saudi Arabia should begin before the core is finalized. The approved fire strategy can affect shaft and lobby arrangements, elevator controls, power supplies and the way building teams coordinate acceptance testing.
The practical task is to turn that strategy into clear requirements for the architect, fire consultant, electrical engineer and elevator supplier. This guide identifies the decisions to document; the project professionals and approving authority determine the applicable design requirements.
Confirm the code basis and building classification
Ask the fire consultant to record the applicable code edition, occupancy, building configuration and authority requirements. The Saudi General Building Code and Saudi Fire Protection Code are official starting references for the building’s fire-safety design.
Do not decide the elevator arrangement from a height threshold quoted without its code context. Ask which requirements apply to this building and how they are reflected in the approved drawings. Any differences between documents should be resolved through the responsible design team and authority.
Distinguish the roles of the elevators
Normal passenger service, firefighter operation and an approved occupant-evacuation arrangement are different functions. A passenger elevator does not become suitable for evacuation simply because it has a backup power supply.
| Function to discuss | Design question |
|---|---|
| Normal passenger service and fire recall | What is the approved response to each fire-alarm condition? |
| Fire-service operation, where required | Which cars, controls, protected spaces and power arrangements are specified? |
| Occupant evacuation, if part of an approved strategy | What additional provisions, supervision and operating procedures apply? |
Define these functions in the tender rather than relying on a general label such as “fireproof elevator.” Building users should follow the building’s emergency plan; a procurement guide is not an instruction to use ordinary passenger lifts during a fire.
Agree the alarm and recall sequence
The elevator controls and fire-alarm system need a coordinated sequence. Ask the designers and suppliers to document the required inputs, destinations, operating modes and reset conditions. The relevant recall levels and responses must come from the approved strategy, not an assumption that every car always returns to the ground floor.
- Identify who supplies each interface and connecting cable.
- Define how alarm conditions are communicated to the elevator controller.
- Coordinate behavior across a group of cars.
- Specify the integrated tests and the parties who witness them.
Coordinate shafts, lobbies and services
The architectural and building-services drawings should show the protection and access arrangements required by the approved design. Confirm the relevant fire resistance, doors, penetrations, water-management provisions and equipment locations.
Check that ventilation and cooling arrangements are compatible with the fire strategy. Review proposed services through or near elevator spaces with the design team rather than treating a shaft as spare space for other systems.
Where standby or emergency power is required, document the loads and operating sequence. Include the support systems needed for the specified elevator operation, such as controls, communication and environmental conditions.
Plan acceptance testing and handover
Prepare a responsibility matrix before installation. It should identify the party responsible for equipment documentation, installation records, electrical checks, alarm integration, inspection arrangements and closing defects.
At handover, provide the owner with the relevant operating and maintenance documents, test records and emergency procedures. Assign responsibility for ongoing testing, maintenance and staff training under the applicable requirements. Keep access devices and control information in accordance with the approved management plan.
Give the supplier an explicit specification
Send the fire strategy, relevant drawings and interface schedule with the tender. Request written confirmation of the selected equipment’s functions and the documentation available for review. Product certification alone should not be confused with approval of the complete building arrangement.
FUJIHD is a China-based manufacturer. Its FUJI elevator range and commercial elevator solutions can be considered against a project’s defined specification. Contact FUJIHD with your drawings and fire-safety brief so that equipment options, interfaces and supply scope can be discussed. Project approval and local installation responsibilities must be confirmed separately.